Danvers Campus Construction Updates
To accommodate students, faculty and staff on the first days of the fall semester - always an exceptionally busy time at NSCC - Campus Police at the Danvers Campus will direct drivers to overflow parking areas as needed.
Construction/parking map and more info
NSCC Danvers Campus Construction Schedule
(Tentative & subject to change)
Please allow for additional time to arrive at your work station or classroom.
September 8, 2009
* Lot 6 available for NSCC use
Week of Sept 14, 2009
*Parking Lots 4 & 5 closed for site prep work
*Allied Health Building main entrance closed
*Parking Lot 7 changed to faculty/staff only with additional handicap accessible spaces
October 2009
*Sections of access road between Berry & Health Buildings temporarily closed due to new electric & gas services
*Foundation excavation & pouring
*Groundbreaking
January/February 2010
*Steel bid & construction over the winter
May-July (Summer) 2010
*Geothermal wells; finish site parking in lot 6; minor expansion of lot 7; by next summer, building will be enclosed and work will commence inside the building; renovation of IT area in current Health Professions building.
August 2010-July 2011
*Approximately one year for inside construction
August 2011- December 2011(TBD)
*Finish site work and move existing staff from Aggie and current Health Professions.
Building open for Fall 2011 or Spring 2012 semester classes TBD.
For further information, contact Cathy Anderson, Special Assistant to the President at canderso@northshore.edu.